Decision Summary

  • Case Ref: FS50073127
  • Date: 01/03/2006
  • Public Authority: Department of the Environment (NI)
  • Summary: On 12 March 2005 the complainant requested information related to the granting of planning permission to store asbestos at Crosshill Quarry. The information was provided on 9 May 2005, outside the 20 working day time limit, and so the commissioner has judged the Department to be in breach of section 10 of the Act.
  • View PDF of Decision Notice: [1]